Las Vegas Athletics ballpark passes halfway mark as Bally's resort financing lags
The A's $2.1 billion Las Vegas Strip ballpark is more than halfway built, while officials raise alarm over financing delays at the neighbouring Bally's resort.
Construction on the Athletics’ $2.1 billion ballpark on the Las Vegas Strip is a little more than halfway completed, according to the Las Vegas Review-Journal. The Mortenson-McCarthy construction joint venture is on pace to open the 33,000-seat stadium by its Feb. 29, 2028 completion deadline.
Crews have hoisted three of the ballpark’s five steel roof trusses into place, and builders expect to install the final truss before the end of this year.
Bally’s financing delays
The ballpark occupies approximately nine acres of the 35-acre former Tropicana site, while Bally’s Corporation controls the remaining 26 acres. Under the site’s master plan, the podium and plaza of a new Bally’s resort and casino will serve as the main pedestrian corridor linking the Strip to the stadium’s front gates.
Officials sounded the alarm over Bally’s ongoing financing delays during a contentious Las Vegas Stadium Authority meeting earlier this month. Construction on the resort’s north-of-$200-million podium and entrance plaza must advance soon to ensure smooth game-day foot traffic.
Site landlord Gaming and Leisure Properties (GLPI) has set aside $125 million and is considering increasing its financing to $250 million. The additional funding remains conditional on Bally’s and the A’s resolving unspecified outstanding business matters.
A’s senior advisor Sandy Dean confirmed the team is preparing contingency plans, including a temporary entry plaza, so that opening day crowds are not forced to navigate an unfinished construction zone.
Funding
The Athletics have spent nearly $700 million building the ballpark so far, with the project funded by private sources to date. Remaining costs will be financed through a $300 million construction loan from Goldman Sachs and U.S. Bank, private investment, personal seat license sales and up to $380 million in public funding. The club expects to have spent about $1.2 billion on construction by the time public money is drawn, which it anticipates will happen in mid-2027.